WestConnex New M5 – MOC1 Buildings

Design & Engineer Stage Scaffolding System
- OVERVIEW

PROJECT TYPE

Public Infrastructure (Design & Engineer Stage Scaffolding System)


PROJECT LOCATION

WestConnex New M5 - MOC1 Buildings, Sydney NSW


DURATION

Jan 2019 - Aug 2019


CLIENT

CPB Dragados Samsung Joint Venture

PROJECT SUMMARY

Delivered by Sydney Motorway Corporation as a series of separate projects, the 33km motorway is to connect Sydney’s western and south-western suburbs with the Sydney CBD, Sydney Airport and Port Botany. The project will ease congestion, provide occupations and connect surrounding communities. The works are scheduled to be completed by November 2019.

An-CO supplied and installed internal support and access scaffold to the five ventilation shaft buildings, each reaching 25 meters in height. The scaffold enabled the safe installation of precast shaft wall panels and provided support for formwork to intermittent floors throughout the shafts. The Scaffold also provided safe access and temporary support for M&E teams to install cabling, ducting, attenuators, dampers and extractor fans.

OVERVIEW

TBC

OUTCOME

TBC

Other Projects

WestConnex New M5 – MOC3 Buildings
Delivered by Sydney Motorway Corporation as a series of separate projects, the WestConnex New M5 project will run from the existing M5 East corridor at Beverly Hills via twin tunnels to St Peter’s, providing improved access to the airport, South Syd
WestConnex New M5 – MOC2 Buildings
The Bexley Motorway Operations Complex will be located within the existing M5 linear parkland alongside Bexley Road and will have an approximate height of 13 metres from ground level. The Bexley Motorway Operations Complex is designed to create minimal vi
Commonwealth Games Village
Gold Coast 2018 Commonwealth Games Village 14-hectare mixed-use urban renewal project sits at the heart of the Gold Coast Health and Knowledge Precinct and performed a central role in hosting the 2018 Commonwealth Games athletes. Formerly known as Parklan
Sydney Metro Martin Place Station
As the new Martin Place Station is built underground, the integrated station development will be able to be built above the station at the same time. This helps reduce community impacts and allows for the buildings to be completed close to when Sydney Met
Sydney Metro West
An-Co delivered all scaffolding access solutions for the TBM build and demobilisation works at Rosehill and Sydney Olympic Park for Gamuda, supporting the assembly and disassembly of tunnel boring machines.
Chatswood Metro Towers
An-Co provided access solutions for the remediation works at Chatswood Metro Towers, working alongside RM Watson to support the replacement of combustible cladding as part of the Government remediation program. The scope comprised seven mast climber units
Sydney Metro East
An-Co delivered all major scaffolding works across the Eastern Tunnelling Package, including critical site access solutions into the east and west shafts at the Hunter Street Station site. Over 450 tonnes of scaffolding were installed across the project,

East Coast based access specialist - engineered scaffolding, mast climbing, plant hire and swinging stages.

Backed by quality, integrity, honesty and respect